重庆交通大学学报(自然科学版) ›› 2014, Vol. 33 ›› Issue (3): 72-78.DOI: 10.3969/j.issn.1674-0696.2014.03.17

• • 上一篇    下一篇

岸桥并行作业效率约束下泊位与岸桥集成分派

高超锋1,胡志华1,2   

  1. 1.上海海事大学物流研究中心,上海 201306;2.同济大学经济与管理学院,上海 200092
  • 收稿日期:2013-07-18 修回日期:2014-03-06 出版日期:2014-06-15 发布日期:2015-01-22
  • 作者简介:高超锋(1988—),男,江西抚州人,硕士研究生,主要从事港口物流运作优化方面的研究。E-mail:gaochaofeng2007@126.com
  • 基金资助:
    国家自然科学基金项目(71101088) ;国家自然科学基金面上项目(71171129) ;上海市大文科研究生学术新人培育计划( wk2013001 )

Berth-Crane Allocation Constrained by Parallel Operation Efficiency of Quay Cranes

Gao Chaofeng1 , Hu Zhihua1,2   

  1. 1.Logistics Research Center, Shanghai Maritime University , Shanghai 201306 , China; 2.School of Economics & Management , Tongji University , Shanghai 200092 , China
  • Received:2013-07-18 Revised:2014-03-06 Online:2014-06-15 Published:2015-01-22

摘要: 针对多个岸桥并行作业时的相互干扰而影响岸桥工作效率的问题,研究了岸桥并行作业效率约束下船舶作业 泊位分派和岸桥分配优化的方法。建立了以船舶在港惩罚成本最小为目标的混合整数线性规划模型,引人不同作 业环境下的干扰因子和偏离最佳靠泊泊位的惩罚系数,分析了岸桥工时和惩罚成本的影响。研究了并行作业岸桥 数量变化对效率的影响。算例分析表明:虽然岸桥并行作业的数量增多能够加快装卸,减少船在港惩罚成本,但是 会降低岸桥工作效率,增加岸桥总工时,从而增加集装箱港口的运作成本。

关键词: 港口工程, 泊位与岸桥的集成分配, 并行作业, 干扰, 混合整数规划, 多目标优化

Abstract: Regarding the problem that the interferences among parallel operational cranes affect the efficiencies of cranes , the strategies for berth allocation and quay assignment were studied , considering the constraints of efficiency of parallel operational cranes. A mixed integer programming linear model was established to minimize the penalty costs when vessels stayed waiting for operations. Interfer ence factors in different operation environments and penalty coefficients off the optimal berthing position were introduced in the model to analyze the effects of varying the working hours of cranes and penalty costs. And the effects of the numbers of parallel operational cranes on the efficiency of these Cranes were further studied. The case studies show that more parallel operational Cranes can speed up the container handling tasks and reduce the penalty costs of vessels waiting for operations; however, it reduces the operation efficiencies of cranes , which increases the working hours of cranes and total operation costs of port.

Key words: port engineering, berth -crane allocation problem ( BCAP) , parallel operation, interference, mixed integer linear programming, multi-objective optimization

中图分类号: