中文核心期刊
CSCD来源期刊
中国科技核心期刊
RCCSE中国核心学术期刊

重庆交通大学学报(自然科学版) ›› 2014, Vol. 33 ›› Issue (4): 142-146.DOI: 10.3969/j.issn.1674-0696.2014.04.29

• • 上一篇    下一篇

基于区间值模糊推理的公路工程定额拟定

刘燕1,钱育锋2,马海燕2,张春燕2,李志辉3   

  1. 1.重庆交通大学 管理学院,重庆400074;2.四川省交通厅 交通建设工程造价 管理站,四川 成都610041; 3.深圳高速工程顾问有限公司,广东 深圳 518034
  • 收稿日期:2012-11-01 修回日期:2013-12-18 出版日期:2014-08-15 发布日期:2015-03-10
  • 作者简介:刘燕(1965—),女,四川荣县人,教授,注册造价师,主要从事工程项目管理、工程造价管理方面的教学与研究工作。E-mail: liuyan_cquc@163.com。
  • 基金资助:
    四川省交通科技项目(2009B25-1)

Method for Highway Engineering Quota Formulation Based on Interval-Valued Fuzzy Reasoning Theory

Liu Yan1, Qian Yufeng2, Ma Haiyan2, Zhang Chunyan2, Li Zhihui3   

  1. 1. School of Management, Chongqing Jiaotong University, Chongqing 400074, China; 2. Transportation Construction Project Cost Management Station, Sichuan Department of Transportation, Chengdu 610041, Sichuan, China; 3. Shenzhen Expressway Engineering Consultants Co. Ltd., Shenzhen 518034, Guangdong, China
  • Received:2012-11-01 Revised:2013-12-18 Online:2014-08-15 Published:2015-03-10

摘要: 根据工效学理论分析了公路工程定额编制中工料机消耗影响因素及其权重,应用区间值模糊推理,研究了拟编制定额与相似定额综合相似度的确定方法和 工料机消耗量估算模型,将上述方法应用于汶川震后恢复重建工程的定额拟定,并把拟定成果与采用传统测定方法所得的结果进行比较,其定额基价误差仅为 1.92%。结果表明区间值模糊推理用于公路工程定额的编制,能满足工程造价确定与控制要求,且能充分利用现有丰富定额资源,兼顾专家的知识和经验,适应公路 工程项目单件性的特点,是一种持续改进的实用方法。

关键词: 管理工程, 区间值模糊推理, 工料机消耗量, 特征影响因素, 综合相似 度

Abstract: The analysis of the quantity of construction material and working hours of labor and mechanical consumption influencing factors and their weights in the highway engineering quota formulation process was carried out based on the theory of ergonomics. Using the interval- valued fuzzy reasoning method, the method for determining the integrated similarity between the wanted document quota and other similarity in the published quotas was studied, and the estimation model for quantity working hours, construction material and mechanical consumption was also studied. The above research results were applied in the quota fixing of highway reconstruction project after Wenchuan Earthquake. Compared with the results obtained by the traditional field survey method, the error was only 1.92% of its quota fixed base price. The results indicate that the interval-valued fuzzy reasoning can be used to document highway engineering quota and to meet the requirement of highway project costs determination and controls. The proposed method can take full advantage of the rich existing resources and take the knowledge and experience of experts into account at the same time, which is adapt to the characteristics of a single piece of highway projects. The proposed method is a practical approach with continuous improvement.

Key words: management engineering;interval-valued fuzzy reasoning, quantity of construction material and working hours of labor and mechanical consumption, characteristic influence factors, integrated similarity