摘要: 在对澜沧江橄榄坝河岸坍塌原因进行了详细分析的基础上.提出河岸治理应以控制落水期中水流向为主,综合考虑航运、防洪、护岸等因素.通过模型试验研究,根据治理原则而采取的工程措施是可行的.
关键词: 河岸坍塌, 护岸工程, 中水流向
Abstract: The paper is based on detailed analysis of the cause for the cave of Gan Lanba river bank of Lanchang-Mekon River.It is suggested that the control of flow direction median during the low water level period plays a leading role in the river bank.Training considering navigation, flood proof and bank paving comprehensively, through Model-testing research various constructing methods adopted according to this regulation is proved to be practicable.
Key words: the caving of river bank, riverbank protecting project, flow direction median
中图分类号:
U6178
庹瑶, 许光祥, 疏玉清. 澜沧江橄榄坝河段护岸工程试验研究[J]. 重庆交通大学学报(自然科学版), 1999, 18(3): 105-109.
TUO Yao, XU Guang-xiang, SU Yu-qing. The Testing Research of River Bank-Protecting Project for Gan Lanba River Reach of Lanchang-Mekon River[J]. Journal of Chongqing Jiaotong University(Natural Science), 1999, 18(3): 105-109.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://xbzk.cqjtu.edu.cn/CN/
http://xbzk.cqjtu.edu.cn/CN/Y1999/V18/I3/105