地铁循环荷载作用下隧道周边软黏土动力响应特性研究

蒲黍絛1,叶斌2,王海诚1,郭维祥1,陈再谦1   

  1. (1. 中国电建集团贵阳勘测设计研究院有限公司, 贵州 贵阳 550081; 2. 同济大学 地下建筑与工程系, 上海 200092)
  • 收稿日期:2017-11-10 修回日期:2018-10-15 出版日期:2019-02-22 发布日期:2019-02-22
  • 作者简介:蒲黍絛(1992—),男,贵州铜仁人,工程师,主要从事地铁动力响应方面的研究。 E-mail: 997110232@qq.com。 通信作者:叶斌(1977—),男,上海人,副教授,博士,主要从事砂土液化方面的研究。E-mail: yebinmail@1977gmail.com。

Dynamic Response Characteristics of Soft Clay around Tunnel under Subway Cyclic Loads

PU Shutao1, YE Bin2, WANG Haicheng1, GUO Weixiang1, CHEN Zaiqian1   

  1. (1. Guiyang Survey Design & Research Institute Co. Ltd., Power Construction Corporation of China, Guiyang 550081, Guizhou, P. R. China; 2. Department of Geotechnical Engineering, Tongji University, Shanghai 200092, P. R. China)
  • Received:2017-11-10 Revised:2018-10-15 Online:2019-02-22 Published:2019-02-22

摘要: 以上海地铁9号线为工程背景,在现场实测的基础上,采用计算程序DBLEAVES对地铁循环荷载作用下隧道周边软黏土的动力响应特性进行了研究。 研究表明:在地铁循环荷载作用下,隧道周边软黏土的沉降规律为绕隧道向外弧形扩散,沉降值越来越小,直至影响范围边界,地表沉降呈沉降槽形式发 展;最大沉降发生在隧道正下方,通过拟合得出土体的最终沉降量为19.8 mm;加速度响应方面,其空间分布形式同沉降规律,隧道右下方土体内的加速 度及其衰减速度均略大于右上方土体;在循环荷载加载初期,土体内的超孔隙水压力上升很快,几乎呈线性发展;随着循环次数的增加,逐渐趋于稳定并 向边界消散;超孔隙水压力比土体的有效应力小得多,隧道下方土体在循环荷载作用下不会发生液化现象。

关键词: 隧道工程, 地铁隧道, 循环荷载, 动力响应, 数值计算

Abstract: Based on the project of Shanghai Metro Line 9 and the filed measurement, a calculation program DBLEAVES was adopted to study the dynamic response characteristics of soft clay around tunnel under subway cyclic loads. The research results show that: under subway cyclic loads, the settlement law of soft clay around tunnel is arc spreading out around tunnel and the value is getting smaller and smaller until the boundary of influence. Ground settlement develops in the form of settlement trough. The largest settlement occurs directly below the tunnel and the final settlement of soil around tunnel is 19.8mm by fitting. In terms of acceleration response, the spatial distribution rule of acceleration response is the same as that of settlement. Acceleration and the decay rate of the right-bottom soil around tunnel are slightly larger than that of top-right soil. At the beginning of cyclic loads, excess pore water pressure of soil is rising quickly with nearly linear development and gradually intends to be stabilized and dissipated to the boundary with the increase of the number of cycles. Excess pore water pressure is much smaller than the effective stress of soil, so the liquefaction phenomenon will not happen below the tunnel under subway cyclic loads.

Key words: tunnel engineering, subway tunnel, cyclic loads, dynamic response, numerical calculation

中图分类号: