重庆交通大学学报(自然科学版) ›› 2008, Vol. 27 ›› Issue (2): 225-227,289.
• • 上一篇 下一篇
范小伟, 徐林生
收稿日期:
修回日期:
出版日期:
发布日期:
作者简介:
FAN Xiao-wei, XU Lin-sheng
Received:
Revised:
Online:
Published:
摘要: 根据隧址区工程地质特征,建立了长冲隧道进口段的有限元模型;模拟了台阶分部法和CD工法开挖隧道的过程,通过对围岩的位移和应力特征、屈服接近度和支护结构受力特征的分析,从施工工序和施工力学角度对两种开挖方法进行了比较,结果表明设计推荐采用的CD工法较台阶分部法没有明显的优势。
关键词: 长冲隧道, 台阶分部法, CD工法, 数值模拟
Abstract: Based on engineering geological feature of tunnel setting, a finite element of entrance of Changchong tunnel is established, which can simulate the construction process under the bench method and CD method. Displacement, stress, characteristics of yield degree of surrounding rock and the force of supports structure are analyzed. Construction process and stress of these two methods are compared so as to optimize the practical construction scheme. The result indicates that bench method is better than CD method.
Key words: Changchong tunnel, bench method, CD method, numerical modeling
中图分类号:
U459.2
范小伟, 徐林生. 长冲隧道进口段开挖方法的优化分析[J]. 重庆交通大学学报(自然科学版), 2008, 27(2): 225-227,289.
FAN Xiao-wei, XU Lin-sheng. Optimal Analysis on Entrance Construction Scheme for Changchong Tunnel[J]. Journal of Chongqing Jiaotong University(Natural Science), 2008, 27(2): 225-227,289.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://xbzk.cqjtu.edu.cn/CN/
http://xbzk.cqjtu.edu.cn/CN/Y2008/V27/I2/225