重庆交通大学学报(自然科学版) ›› 2016, Vol. 35 ›› Issue (1): 184-190.DOI: 10.3969/j.issn.1674-0696.2016.01.35

• 载运工具与机电工程 • 上一篇    

地铁机电安装工程施工虚拟优化管理技术研究

段晓晨1,代鹏飞1,汪辉2   

  1. 1. 石家庄铁道大学,河北 石家庄 050043;2. 铁道第二勘察设计院集团有限公司 杭州分院,浙江 杭州 310000
  • 收稿日期:2015-03-23 修回日期:2015-07-23 出版日期:2016-02-20 发布日期:2016-04-21
  • 作者简介:段晓晨(1962—),男,山东招远人,教授,博士,主要从事工程经济与造价管理方面的研究。E-mail:duanxch888@sohu.com。
  • 基金资助:
    河北省高层次人才资助项目(2013429102);中铁建集团总公司科技计划项目(中铁建科201252);河北省交通厅科技计划项目(冀交科教2013559-28);河北省软科学工程建设管理研究基地(冀科教2012567);河北省教育厅人文社科重点研究基地(工程建设管理)(冀教201426)

Virtual Optimization Management Technology in Construction of Subway Electromechanical Installation Project

DUAN Xiaochen1, DAI Pengfei1, WANG Hui2   

  1. 1. Shijiazhuang Tiedao University, Shijiazhuang 050043, Hebei,P.R.China; 2. Hangzhou Branch of 2nd Railway Design Group Company, Hangzhou 310000, Zhejiang,P.R.China
  • Received:2015-03-23 Revised:2015-07-23 Online:2016-02-20 Published:2016-04-21
  • Contact: 代鹏飞(1990—),男,河北邢台人,硕士研究生,主要从事工程经济与造价管理方面的研究。E-mail:daipengfeihappy@163.com。

摘要: 在总结地铁机电系统工程施工特点的基础上,针对津滨地铁中山门西段机电安装工程的实际,将复杂系统理论挣值理论(EVM)、显著性成本理论(CS)、BP神经网络(BPNN)、灰色预测,虚拟现实技术和动态优化管理技术运用到施工管理的过程中,开发和利用相应的虚拟动态优化管理系统,进行工程的虚拟可视化的管理。首先在施工之前,建立各工种、各专业接口、协同、立体交叉作业的虚拟静态优化管理系统;其次,在施工过程中建立动态的优化管理系统,以重点控制施工项目进行EVM分析和PDCA循环控制,分析存在的问题,建立控制措施数据资料库,方便进行施工管理和做出决策,从而实现管理的科学化、信息化。

关键词: 机电工程, 地铁机电安装, 虚拟优化技术, 复杂系统施工管理

Abstract: Based on the summary of construction characteristics of subway electromechanical project, according to the actual problems of the Jinbin subway project of western section of Zhongshanmen, complex system theories (Earned Value Management (EVM), Cost-significant(CS), Back-Propagation Neural Network (BPNN), Gray model (GM) ), virtual reality techniques and dynamic optimized management technique were applied in the process of construction management. The corresponding virtual dynamic optimized management system was developed to realize the virtual visualization management of the project. Before the subway construction, the virtual static optimized management system was set up, which had the characteristics of multi-work, multi-professional, multi-coordination, mutual intercrossing and paralleling, multi-dimension and multi-interference. In the process of subway construction, the dynamic optimized management system was established to focus on the key control project to carry out EVM analysis and PDCA cycle control. The existed problems were analyzed and the data repository of control measures was established, which was convenient for construction management and decision-making, so as to realize the scientific and informatization management.

Key words: electromechanical engineering, subway electromechanical installation, virtual optimization techniques, construction management of complex system