重庆交通大学学报(自然科学版) ›› 1999, Vol. 18 ›› Issue (4): 54-60.
• • 上一篇 下一篇
顾安邦, 常英, 乐云祥
收稿日期:
出版日期:
发布日期:
作者简介:
GU AN-bang, CHANG Ying, YUE Yun-xiang
Received:
Online:
Published:
摘要: 以重庆黄花园嘉陵江大桥施工控制的具体实践为例,介绍了该桥施工控制过程中所采用的控制原理和方法.对于误差分析,定义受控对象和控制变量,确定目标函数,采用了控制论中的随机最优控制理论,实现了计算机对施工的全过程控制,使大桥的下游幅顺利合龙.
关键词: 黄花园大桥, 预应力连续刚构桥, 施工控制
Abstract: The construction control process of Chongqing Huang-hua-yuan Jia Lin River bridge is taken as an example in this paper.The control principle and method which used in construction control is stated.The controlled object and control variable are defined and objective function is established by stochastic optimal control theory of engineering cybernetics for the error analysis.So the whole construction control is achieved by computer as a measure of joining the two section of a bridge successfully.
Key words: Huanghuayuan bridge, prestressed continuous rigid frame bridge, construction control
中图分类号:
U448.23
顾安邦, 常英, 乐云祥. 重庆黄花园嘉陵江大桥施工控制[J]. 重庆交通大学学报(自然科学版), 1999, 18(4): 54-60.
GU AN-bang, CHANG Ying, YUE Yun-xiang. The construction control for Chongqing Huanghuayuan Jialin River bridge[J]. Journal of Chongqing Jiaotong University(Natural Science), 1999, 18(4): 54-60.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://xbzk.cqjtu.edu.cn/CN/
http://xbzk.cqjtu.edu.cn/CN/Y1999/V18/I4/54