[1]陈开利,余天庆,习刚. 混合梁斜拉桥的发展与展望[J]. 桥梁建设, 2005(2) : 1-4.
Chen Kaili,Yu Tianqing,Xi Gang. Development and prospective of hybrid girder cable-stayed bridge [J]. Bridge Construction,2005(2) : 1-4.
[2]石雪飞,项海帆. 斜拉桥施工控制方法的分类分析[J]. 同济大学学报,2001, 29(1) : 55-59.
Shi Xuefei,Xiang Haifan. Analysis of construction control systems of cable-stayed bridge[J]. Journal of Tongji University,2001,29(1) : 55-59.
[3]黄冰释,唐守峰,赵灿晖. 鄂东大桥施工期结构行为与施工监控关键技术[J]. 重庆交通大学学报: 自然科学版,2010,29 (5) :688-692.
Huang Bingshi,Tang Shoufeng,Zhao Canhui. Structure behavior and construction monitoring key technology in construction of Edong Changjiang River Bridge[J]. Journal of Chongqing Jiaotong University: Natural Science,2010, 29(5) : 688-692.
[4]Li Qiao,Dong Xuewu,Huang Can,et al. Sensitivity Analysis of Structural Parameters for Super-Span Cable-Stayed Bridge and Its Application[C]. Taipei: The 11th East Asia-Pacific Conference on Structural Engineering & Construction, 2008.
[5]黄灿,卜一之,张清华. 特大跨度斜拉桥施工几何控制原理的数值验证[J]. 中国工程科学, 2009, 11(1) : 87-90
Huang Can,Bu Yizhi,Zhang Qinghua. Numerical verification of geometry control theory of the construction for super-span cablestayed bridge [J]. Engineering Sciences,2009,11(1) : 87-90.
[6]翟世鸿,张照霞. 国内超大跨度钢斜拉桥上部结构施工控制探讨[J]. 中外公路, 2006, 26(1) : 108-112.
Zhai Shihong,Zhang Zhaoxia. Discussion of the construction control of the upper structure of domestic super-span steel cable-stayed bridge[J]. Journal of China & Foreign Highway, 2006, 26(1) : 108-112.
[7]Manabe Y,Hirahara N,Mukasa N,et al. Accuracy Control on the Construction of Tatara Bridge[C]. Malmo Sweden: IABSE Conference,1999.
[8]Yanaka Y,Takazawa T,Hirahara N. Erection of the Tatara Bridge's Superstructure[C]∥Long-Span and High-Rise Structures. Switzerland:IABSE,1998: 75-80.
[9]李乔,卜一之,张清华. 基于几何控制的全过程自适应施工控制系统研究[J]. 土木工程学报,2009,42(7) : 69-77.
Li Qiao,Bu Yizhi,Zhang Qinghua. Whole-procedure adaptive construction control system based on geometry control method [J]. China Civil Engineering Journal,2009,42(7) : 69-77.
[10]秦顺全. 无应力状态控制法———斜拉桥安装计算的应用[J].桥梁建设, 2008(2) : 13-16.
Qin Shunquan. Application of unstressed state control method to calculation for erection of cable-stayed bridge [J]. Bridge Construction,2008(2) : 13-16.
[11]李乔,卜一之,张清华,等. 大跨度斜拉桥施工全过程及几何控制概论与应用[M]. 成都: 西南交通大学出版社,2009.
Li Qiao,Bu Yizhi,Zhang Qinghua,et al. Conspectus of the Geometry Control Method of the Whole-Procedure of Long-Span Cable-Stayed Bridge and Application[M]. Chengdu: Southwest Jiaotong University Press,2009.
[12]谢明志. 特大跨度混合梁斜拉桥全过程监控中的误差控制[D]. 成都: 西南交通大学, 2011.
Xie Mingzhi. Error-Control of Whole-Procedure Construction Control in Super Long-Span Hybrid Girder Cable-Stayed Bridge[D].Chengdu: Southwest Jiaotong University,2011. |