中文核心期刊
CSCD来源期刊
中国科技核心期刊
RCCSE中国核心学术期刊

Journal of Chongqing Jiaotong University(Natural Science) ›› 2022, Vol. 41 ›› Issue (02): 84-94.DOI: 10.3969/j.issn.1674-0696.2022.02.13

• Transportation Infrastructure Engineering • Previous Articles     Next Articles

Influence Analysis of Shield Construction Parameters Controlling on Ground Settlement in Sandy Pebble Stratum Based on Grey Theory

WEI Shengda1, LIU Danna1, PENG Xin1, LYU Yan2, WANG Wei3   

  1. (1. China Communication North Road and Bridge Co., Ltd., Beijing 100024, China; 2. College of Construction Engineering, Jilin University, Changchun 130026, Jilin, China; 3. School of Civil Engineering, Changchun Institute of Technology, Changchun 130012, Jilin, China)
  • Received:2020-05-26 Revised:2020-07-30 Published:2022-02-21

基于灰色理论的砂卵石地层盾构施工参数控制对地表沉降影响分析

韦生达1,刘丹娜1,彭鑫1,吕岩2,王伟3   

  1. (1. 中交路桥北方工程有限公司,北京 100024; 2. 吉林大学 建设工程学院,吉林 长春 130026; 3. 长春工程学院 土木工程学院,吉林 长春 130012)
  • 作者简介:韦生达(1982—),男,广西南宁人,高级工程师,主要从事隧道工程方面的工作。E-mail:120555010@qq.com 通信作者:王伟(1982—),男,吉林长春人,副教授,博士,主要从事岩土工程方面的研究。E-mail:16695496@qq.com
  • 基金资助:
    中交路建科技研发项目(ZJLJ-2018-44)

Abstract: In order to reveal the sensitivity of ground settlement to different shield construction parameters, taking the shield tunnel between Laifeng Road station and Fengxi station of Chengdu metro line 17 as an example, the measured data of 9 control parameters, such as total thrust, cutter head torque and synchronous grouting pressure were analyzed by using grey theory. The research results show that the three most important factors affecting the sensitivity of ground settlement to shield construction parameters are propulsion speed, grouting pressure or grouting amount and screw machine speed in order. When shield construction is carried out in the water rich sandy pebble stratum in Chengdu area, the control range of total thrust of shield is between 19000~41000 kN, the control range of cutter head torque is between 2 000~23 000 kN·m, and the synchronous grouting pressure is between 1~3 bar. The proposed grey correlation analysis model objectively and accurately reflects the relationship between the control of shield construction parameters in water rich sandy pebble stratum and the ground settlement.

Key words: tunnel engineering; geotechnical engineering; sandy pebble stratum; shield; construction parameters; ground settlement; grey theory

摘要: 为了揭示地面沉降对不同盾构施工参数的敏感性,以成都地铁17号线来凤路站—凤溪站盾构区间隧道为例,采用灰色理论对总推力、刀盘扭矩、同步注浆压力等9项控制参数的实测数据进行分析。研究结果表明:地面沉降对盾构施工参数敏感性最主要的3个因素依次为推进速度、注浆压力(注浆量)和螺旋机转速;在成都地区富水砂卵石地层中进行盾构施工时,盾构总推力控制范围为19 000~41 000 kN,刀盘扭矩控制范围为8 000~23 000 kN·m,同步注浆压力为1~3 bar;灰色理论模型能客观、准确地反映富水砂卵石地层盾构施工参数控制与地面沉降之间的关系。

关键词: 隧道工程;岩土工程;砂卵石地层;盾构;施工参数;地面沉降;灰色理论

CLC Number: