Abstract: The difference between activity-on-arrow network and activity-on-node network is the symbol exchange,which brings the variations on the time index calculation and critical path. These variations are caused by the dummy activity in activity- on-arrow network; hence,the main difference between activity-on-arrow network and activity-on-node network lies in whether the dummy activity exists in activity-on-arrow network. Taking an example,the differences are caused by the dummy activity. Dummy activity is important in the application of network planning.
Key words: activity-on-node network, activity-on-arrow network, dummy activity
摘要: 单代号网络图与双代号网络图区别的主要形式是其符号含义的互换。由于符号含义互换带来它们之间某些 时间参数计算和关键线路确定的方法不同,但是这些不同都是当双代号网络图存在虚工作时引起的。所以单双代 号网络图除符号含义不同之外,其时间参数计算的实质区别取决于双代号网络图中有无虚工作。针对网络计划一 实例分析了虚工作造成的实质性区别,说明了这种实质性的区别在网络计划应用中的重要性。
关键词: 单代号网络图, 双代号网络图, 虚工作
CLC Number:
U415.2
TU721.3
Wei Daos-heng. Differences between Activity-on-Arrow Network and Activity-on-Node Network Based on Dummy Activity[J]. Journal of Chongqing Jiaotong University(Natural Science), 2012, 31(4): 819-823.
魏道升. 论虚工作是单双代号网络图的实质性区别[J]. 重庆交通大学学报(自然科学版), 2012, 31(4): 819-823.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://xbzk.cqjtu.edu.cn/EN/10.3969/j.issn.1674-0696.2012.04.21
http://xbzk.cqjtu.edu.cn/EN/Y2012/V31/I4/819