Journal of Chongqing Jiaotong University(Natural Science) ›› 2006, Vol. 25 ›› Issue (4): 44-48.
Previous Articles Next Articles
HUANG Long-xian1,YANC Hu-gen2
Received:
Revised:
Online:
Published:
黄龙显1,杨虎根2
作者简介:
Abstract: For Banpo Bridge in Liang-wang Expressway,the mechanical behaviors of hollw pier under the high filled with soil are analyzed.The soil pressure on the pier is simplified as a trapezoid loads.The computed results indicate that the FEM modle Carl effectively describe the mechanical state of hollow peir.
Key words: hollow pier;high filling soil;trapezoid loads, 3D finite element analysis
摘要: 以重庆梁万路半坡大桥右线为例,对变截面空心桥墩在高填土作用下的受力行为进行了分析,通过指定荷载 梯度模拟填土压力,计算结果全面反映了钢筋硷变截面箱形墩的受力状况.
关键词: 钢筋砼箱形变截面墩, 高填土, 荷载梯度, 三维有限元分析
CLC Number:
TU431
HUANG Long-xian,YANC Hu-gen. Structure analysis of holloww peir in high filling soil[J]. Journal of Chongqing Jiaotong University(Natural Science), 2006, 25(4): 44-48.
黄龙显,杨虎根. 填土中的钢筋砼箱形变截面桥墩受力分析[J]. 重庆交通大学学报(自然科学版), 2006, 25(4): 44-48.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://xbzk.cqjtu.edu.cn/EN/
http://xbzk.cqjtu.edu.cn/EN/Y2006/V25/I4/44