Abstract: This article takes high side slope control project of two noth-high cutting slopes between K35 -K36 on the Jitai expressway as example and introduces the engineering practice of prestressed anchorage cable-hanging net sprayed concrete supporting and retainting structure on controlling the dangerous rock and landslid
Key words: high side slope , prestressed anchor line , hanging net sprayed concrete , supporting and retaining structure
摘要: 以济泰高速公路K35-K36之间两段路堑高边坡治理工程为例,介绍预应力锚索-挂网喷射砼支挡结构在 治理危岩、滑坡等地质灾害的工程实践
关键词: 高边坡, 预应力锚索, 挂网喷射砼, 支挡结构
CLC Number:
U417.1+16
U418.5+2
ZHANG Wen-ke , HUANG Xiao-hua , TANG Jian-jun. Analysis of dangerous rock and landslide reinforced control project on Jitai expressway[J]. Journal of Chongqing Jiaotong University(Natural Science), 2002, 21(2): 71-73.
张文科,黄晓华,唐建军. 济泰高速公路危岩滑坡加固治理工程的分析[J]. 重庆交通大学学报(自然科学版), 2002, 21(2): 71-73.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://xbzk.cqjtu.edu.cn/EN/
http://xbzk.cqjtu.edu.cn/EN/Y2002/V21/I2/71