Journal of Chongqing Jiaotong University(Natural Science) ›› 2011, Vol. 30 ›› Issue (6): 1275-1277.DOI: 10.3969/j.issn.1674-0696.2011.06.03

Previous Articles     Next Articles

Impact of Tie-Down Cable on Main Girder of Multi-tower Cable-Stayed Bridge

TANG Ping-jian1,WANG Hong2,WANG Peng2   

  1. 1. School of Civil Engineering & Architecture,Chongqing Jiaotong University,Chongqing 400074,China; 2. China Merchants Chongqing Communications Research & Design Institute Co. Ltd. ,Chongqing 400067,China
  • Received:2011-07-11 Revised:2011-07-19 Online:2011-12-15 Published:2015-01-22

下拉索对多塔斜拉桥主梁的影响

唐平建1,汪宏2,王鹏2   

  1. 1. 重庆交通大学土木建筑学院,重庆400074; 2. 招商局重庆交通科研设计院有限责任公司,重庆400067
  • 作者简介:唐平建(1983—),男,四川遂宁人,硕士研究生,主要从事大跨径桥梁设计理论研究。E-mail:tang_p_jian@163.com。

Abstract: Through the application of the calculation method of the conventional two towers cable-stayed bridge,the simplified static calculation formula of a structural system of multi-tower cable-stayed bridge with tie-down cables is got. Furthermore, a finite element analysis model is established. Taking different set locations of the tie-down cable as parameters,the impact of the tie-down cable layout on the force of main girder is analyzed. The results show that: setting up the tie-down cable can locally increase the axial force on the main girder,but reduce the moment correspondingly; and the bearing on the main beam is less affected by setting up the tie-down cable.

Key words: multi-tower cable-stayed bridge, tie-down cable, main girders, finite element analysis

摘要: 应用常规两塔斜拉桥的计算方法,得出了下拉索体系多塔斜拉桥的简化静力计算公式; 建立了有限元分析模 型,以下拉索的位置设置为参数,分析了下拉索布置对主梁受力的影响。结果表明: 设置下拉索局部地增加了主梁 轴力,但弯矩却相应地减小,对主梁的承载影响较小。

关键词: 多塔斜拉桥, 下拉索, 主梁, 有限元分析