重庆交通大学学报(自然科学版) ›› 2008, Vol. 27 ›› Issue (1): 28-31,36.

• • 上一篇    下一篇

菜园坝大桥B匝道连续刚构桥施工控制

陈思甜, 王志鹏, 刘鹏, 原媛   

  1. 重庆交通大学, 重庆 400074
  • 收稿日期:2006-11-15 修回日期:2006-12-20 出版日期:2008-02-20 发布日期:2016-11-14
  • 作者简介:陈思甜(1963-),男,四川宣汉人,副教授,主要从事桥梁监控、结构分析等研究工作。

Construction Control of Caiyuanba B Ramp Continuous Rigid Frame Bridge

CHEN Si-tian, WANG Zhi-peng, LIU Peng, YUAN Yuan   

  1. Chongqing Jiaotong University, Chongqing 400074, China
  • Received:2006-11-15 Revised:2006-12-20 Online:2008-02-20 Published:2016-11-14

摘要: 结合菜园坝大桥工程实例,对采用分节段悬臂浇筑施工的连续刚构桥梁结构施工控制进行了研究,提出了切实可行的控制方法。对成桥后的收缩徐变影响进行了专门考虑,增设附加预拱度,合拢后合拢误差小,桥面线形顺畅。

关键词: 连续刚构, 施工控制, 收缩徐变

Abstract: The construction control of continuous rigid frame bridges which were constructed by the segmental cantilever method were studied in the light of engineering practice-Caiyuanba B Ramp Bridge, and the feasible control methods were proposed. Furthermore, influences on shrinkage and creep of the large-span bridge during its service was specially analyzed. An additional camber is considered and advised. The better connecting precision is reached, and the smooth linetype of the bridge can be formed.

Key words: continuous rigid frame, construction control, shrinkage and creep

中图分类号: