Application?of?Influence?Matrix?Method?to?Secondary??Cable-Adjustment?of?Cable-Stayed?Bridges

YANG Xing, ZHANGMin, ZHOU Shui-xing   

  1. School?of?Civil?Engineering?&?Architecture,?Chongqing?Jiaotong?University,?Chongqing?400074,?China
  • Received:2008-11-28 Revised:2008-12-20 Online:2009-06-15 Published:2015-04-15

影响矩阵法在斜拉桥二次调索中的应用

杨兴,张敏,周水兴   

  1. 重庆交通大学土木建筑学院,重庆400047
  • 作者简介:杨兴(1985—),男,重庆潼南人,硕士研究生,主要从事桥梁设计理论研究。Email:xingecjtu@163.com。

Abstract: In?order?to?improve?the?structure?security?and?guarantee?the?girder's?safety?in?the?construction?of?cable-stayed?bridges,?cables?should?be?tensioned?twice?and?then?the?expected?completed?state?can?be?achieved?at?last.?A?good?method?is?proposed?to?calculate?the?cable?tension?forces?and?the?adjusted?order.?Based?on?the?theory?of?influence?matrix,?an?optimized?control?model?to?solve?the?second?cable?adjustment?is?established,?and?the?method?of?penalty?function?is?used.?This?method?has?many?advantages,?such?as?high?preciseness,?convenience?and?practice?etc.?,?which?can?also?be?used?to?minimize?the?error?of?the?cable?tension?force?at?the?completed?state.

Key words: cable-stayed bridge , secondary cable-adjustment , completed state , influence matrix method , penalty function method ;

摘要: 在斜拉桥施工过程中为增大结构的安全储备并保证主梁受力安全,对斜拉索采用两次张拉,最终实现预想的 成桥状态,由此提出二次调索施调索力、顺序的计算问题。以影响矩阵理论为基础,建立了二次调索最优控制的数 学模型,采用惩罚函数法求解,该方法计算精确、简便、实用,也可用于成桥后索力的误差调整。

关键词: 斜拉桥, 二次调索, 成桥状态, 影响矩阵法, 惩罚函数法